An article published in Engineering New-Record (ENR) on May 14,
2012 under the title “Fee Holdback Raises Eyebrows” has indeed drawn attention.
The article explains that the design-build team on a U.S. General Services
Administration (GSA) project being constructed in Seattle agreed that the GSA could
withhold 0.5% of the original contract amount, or $330,000, pending the
achievement of energy goals. Specifically, the design-builder, architect, MEP consultant,
and the mechanical and electrical contractors are all at risk for the
achievement of actual energy usage that is 30% less than the ASHRAE 90.1-2007
standard. Measurement will take place over a 12 month period commencing this
September. The article did not address whether the retention of compensation is
the GSA’s sole remedy for the building’s failure to meet the energy goal. If not waived, other remedies could
potentially include recovery from the design-build team of additional energy
costs the GSA incurs.
Awarded in October 2009, the project is now 80% complete and
the design-build team is optimistic that it will meet the goal, according to
comments quoted in the article. The architect speaks positively of the GSA’s
process, calling it a “step in the right direction for the industry.” Others
might more cynically suggest that the GSA took advantage of a bad economy to
force the team to guarantee results. The article notes that competition for the
award was fierce, and the design-builder regarded the hold-back as a cost of
doing business with the GSA.
The GSA’s approach is diametrically opposed to the recommendations
of the American Institute of Architects, which advises both architects and
contractors not to guarantee or warrant the achievement of a sustainability
goal. The AIA’s 2011 Sustainability
Guide explains the obvious: contractors
and architects can design and construct a building, but the owner operates it,
and the owner’s actions are beyond the control of the design and construction
team. If the owner operates the building differently from the assumptions used
during design, performance goals will likely not be met, even if the building
is perfectly constructed.
The design-builder accepted the risk, and allocated it to
the applicable design and construction team members—a sound risk management
approach. The design firm typically expects to share its risks with a
professional liability insurance carrier, but that coverage may not be
available where the team has essentially guaranteed with its expected fee that
certain building performance will be attained. Professional liability insurance
covers a design firm only for its professional negligence and specifically excludes
from coverage damages that arise solely from guarantees and warranties. If the
design firm was not negligent in failing to meet the performance standard, it
could still be held legally liable for breaching the contractual promise, and
damages associated with that breach would not be covered.
Sophisticated building owners understand that when the
construction contractor is required to absorb a risk it cannot control the
construction price goes up, because the contractor will have no choice but to
add a contingency to cover its potential loss. A design team that has agreed to
meet a performance guarantee may be wise to take a similar approach by over-designing
the building systems to increase the likelihood that the operating building
will meet the required performance. Such “over design” will benefit the owner,
but will come at a price that not every owner would be willing to pay. The ENR
article explains that according to the team’s energy modeling, the GSA building
will use 40% less energy than ASHRAE 90.1’s benchmark, providing a 10% cushion
over the 30% less energy usage required by the contract. The GSA’s Seattle
building is chock-full of energy saving systems, some of which were included in
a $1.3 million dollar change order.
The GSA chose not to execute an agreement with an Award Fee
for the achievement of goals, as some other federal agencies have done (recall,
for example, the Pentagon Renovation). Instead, it imposed a penalty: meet the goal or forfeit your money. According to the article, the GSA calls this
an “integrated process” requiring “tremendous collaboration.” The GSA’s
penalty-based process should not be confused with the collaborative and
integrated process others have in mind when they enter into multi-party
Integrated Project Delivery (IPD) agreements.
IPD contracts may not be painless, because the design and construction
team puts its profit at risk to cover the costs of its mistakes, but the IPD contracts
performed to date have incentivized outstanding performance by offering increased
profits, not by denying compensation, for the achievement of project goals.
Design teams are making significant progress in showing that
good design can affect outcomes for building users. Evidence-based design,
where design decisions are based on quantifiable research, is making great
strides in healthcare, and it has applications in retail and other
industries. Certainly, building owners
benefit from designs that are based on delivering predictable outcomes, whether
derived from prior research or from computer-generated energy models. Such
design is here to stay and will only help the industry, but owners, designers,
and contractors alike should consider carefully whether a contractual performance
guarantee is the optimal way to achieve the desired result, given the potential
uninsurable risks, and increased costs to the project.
[See this article also in the June 2012 ConstructionRisk.com Report at www.constructionrisk.com]
This GSA project arrangment is one which I have been speaking about for some time in the context of green building risk. It is inevitable that as sustainability moves (and it HAS to!) from "feel good" to "works good" there will be a push to attach performance outcomes to monies paid for projects. The various organizations involved in the sustainable buildings movement (ASHRAE, USGBC, AIA, etc) have made significant effort to track actual performance over time (LEED 2009's M&V requirement) and quantify sustainability goals (i.e. ASHRAE Std. 189.1). There is also a rapid expansion in the use of mandatory comparative metrics (EPA's Energy Star Portfolio Manager) and comparative analytics and ratings (ASHRAE bEQ Label). Suzanne is correct to point out that design professionals must be mindful of the impacts on their E&O coverage in offering a guarantee of performance. The concerns about how operations can seriously impact on-going performance raised by the AIA cite are very valid. Maybe a debate will bubble up about the potential errors and omissions and cmomissions of operations and how to mitigate those risks? This particular project's one year performance measurement time frame is consistent with the typical "one and done" construction warranty and not unreasonable with respect to the building drifting 'out of tune' over time, especially if maintenance is not kept up to snuff. But I suspect that within the deal there are provisoes that protect the design and construction team from the negligent owner. I think that threat in this instance is minimal since the GSA has other Federal inducements to keeping the building tuned. It will be interesting to see how this works out.
ReplyDeleteBut at the end of the day, somehow somebody has to show something that proves that an investment in sustainability yields a return.